XTX says its first Kajaani data centre has opened with 22.5MW of IT capacity, with a second scheduled for 2027. Power is secured for the first two; the third, under construction for mid-2028, still faces uncertainty over power availability.
The company's migration account is unusually physical: 385 servers, 17,000 drives and 26 tonnes of equipment moved five kilometres over six weeks. The 417PB figure describes storage capacity moved, not a measured volume of data transferred. XTX says that move, one part of a larger migration, caused no downtime. The immediate operational achievement and the expansion constraint sit together: moving hardware can be scheduled; the next campus increment depends on securing electricity. XTX's announcement.